Water Damage Protection

✓ LOW ✓ MODERATE ✓ HIGH
1 Enhancement 1 Overlay 2 Related Controls
Graph
Export ▾

Requirements NIST SOURCE

Protect the system from damage resulting from water leakage by providing master shutoff or isolation valves that are accessible, working properly, and known to key personnel.

Discussion (NIST Supplemental Guidance)

The provision of water damage protection primarily applies to organizational facilities that contain concentrations of system resources, including data centers, server rooms, and mainframe computer rooms. Isolation valves can be employed in addition to or in lieu of master shutoff valves to shut off water supplies in specific areas of concern without affecting entire organizations.

Enhancements NIST SOURCE

PE-15(1) Automation Support LOW MODERATE ✓ HIGH

Detect the presence of water near the system and alert [personnel or roles] using [automated mechanisms].

Discussion

Automated mechanisms include notification systems, water detection sensors, and alarms.

Open full page for PE-15(1) →

Implementation Guidance

Engineering Interpretation

Original engineering commentary written for this explorer — not NIST source text and not authoritative guidance.

No engineering interpretation has been authored for PE-15 yet. This section is architected to receive it — see the Requirements and Assessment sections above for the authoritative NIST source content in the meantime.

Assessment

NIST SP 800-53A REV 5.2.0

Assessment Objectives

  1. the system is protected from damage resulting from water leakage by providing master shutoff or isolation valves;
  2. the master shutoff or isolation valves are accessible;
  3. the master shutoff or isolation valves are working properly;
  4. the master shutoff or isolation valves are known to key personnel.

Examine

[SELECT FROM: Physical and environmental protection policy; procedures addressing water damage protection; facility housing the system; master shutoff valves; list of key personnel with knowledge of location and activation procedures for master shutoff valves for the plumbing system; master shutoff valve documentation; system security plan; other relevant documents or records].

Interview

[SELECT FROM: Organizational personnel with responsibilities for system environmental controls; organizational personnel with information security responsibilities].

Test

[SELECT FROM: Master water-shutoff valves; organizational process for activating master water shutoff].

Overlays

OT/ICS Overlay SP 800-82r3

NIST SP 800-82r3 Appendix F, Table 22. Blank baseline means the control/control enhancement is not selected in that initial OT baseline.

LOW

  • Base control: Included (matches standard baseline)

MODERATE

  • Base control: Included (matches standard baseline)

HIGH

  • Base control: Included (matches standard baseline)
  • Included: (1)

STIGs & CCIs

No STIG checks or CCI mappings are currently loaded for PE-15. This section is architected to display, per product: STIG ID, Finding ID, Severity, Title, Description, Check, Fix, CCI, and NIST control mapping — but nothing is populated here until a real DISA STIG/CCI dataset is ingested.

Learn more about STIG/CCI integration →

Evidence

Potential Evidence — Derived

Categorized from the SP 800-53A "Examine"/"Test" artifact list above by keyword — not an authoritative NIST evidence list.

Policy

  • Physical and environmental protection policy
  • system security plan

Testing

  • Master water-shutoff valves
  • organizational process for activating master water shutoff

Other Records

  • procedures addressing water damage protection
  • facility housing the system
  • master shutoff valves
  • list of key personnel with knowledge of location and activation procedures for master shutoff valves for the plumbing system
  • master shutoff valve documentation
  • other relevant documents or records